How We Assess and Manage Earthquake-Prone Buildings
Find out about our process for dealing with earthquake-prone buildings, from identification through to strengthening.
What earthquake-prone means
A building, or part of a building, is earthquake prone if it is likely to collapse and cause injury or death, or damage to another property, in a moderate earthquake. A moderate earthquake would generate a third of the level of shaking used to design a new building at the same site.
Earthquake-prone buildings are given an earthquake rating, commonly referred to as a percentage of the new building standard (NBS). Earthquake ratings mean the degree to which the building, or part, meets the seismic performance requirements of the Building Code. Buildings that achieve less than a third of the new building standard (below 34% NBS) are considered earthquake-prone.
The earthquake-prone building process
In May 2016, Parliament amended the Building Act 2004 to introduce a nationally consistent approach to the assessment and management of earthquake-prone buildings, including standardised notices and a national public register. This earthquake-prone building process came into force on 1 July 2017.
The earthquake-prone building process can be summarised in five steps:
Identification:
- The Council will identify buildings that are potentially earthquake-prone and notify owners.
- MBIE - Identifying earthquake-prone buildings
What if I am a building owner and have not heard from Council?
Council has viewed our district’s property files and established what buildings could be potentially earthquake-prone. If you haven’t been contacted by Council, then your building does not appear to fall within the scope of the EPB Methodology.
If you have concerns, and you want to confirm that, please email us: buildingcomplianceadmin@westernbay.govt.nz
Assessment:
- Owners of potentially earthquake-prone buildings will then provide more information about their building to the Council.
- The Council will then confirm whether the building is earthquake-prone or not.
Notification:
- Owners of earthquake-prone buildings will receive confirmation from the Council and will be issued an earthquake-prone building notice with a deadline to strengthen or demolish.
- An earthquake-prone building notice must be displayed on the main entrance/s (including entry to each tenancy) to a building, informing the public that it is earthquake-prone, until Council officially notifies the owner the notice can be removed.
- A notice also shows the deadline by when a building must be fixed. The time frame for most buildings in the Western Bay District is 25 years, however, buildings that have been identified as priority buildings have 12.5 years.
Seismic work:
- Owners of earthquake-prone buildings will then carry out seismic work to ensure that their building is no longer earthquake-prone. Fixing an earthquake-prone building involves seismic work. This normally involves strengthening, demolishing, or partially demolishing the building.
Removal of the notice:
- The owners will notify the Council once seismic work has been completed and a code compliance certificate has been issued. The Council will then review the work and inform the building owner that the building is no longer considered earthquake-prone. The notice can then be removed from the building.
- Council will then update the MBIE earthquake-prone building register.